(1) This Procedure is governed by the Work, Health, Safety and Wellbeing Policy. (2) This Procedure applies to new work managed by Development and Capital Projects and work managed by Properties and Facilities or Business Units. (3) Designers shall ensure that anything they design, is designed to minimise risks to health and safety. (4) New work managed by Development and Capital Projects is understood as being designed. However, whole room or facility refurbishments managed by Properties and Facilities or work areas will also be considered as designs, even if the work involves the like-for-like replacement of the room or facility contents because: (5) Although the scope of this procedure does not consider changes smaller than room or facility refurbishments from a design perspective, ACU will always ensure that any changes maintain or improve the management of relevant WHS risks. The risk assessment process is outlined in the WHS Risk Management Procedure. (6) Development and Capital Projects shall ensure that, during the engagement of architects (or other designers), the contract clearly identifies the engaged party as the designer. (7) During the design process, hazards should be identified which are likely to arise during the following stages: (8) To ensure there is clear record of the Safety in Design process for refurbishment works, the WHS Design Risk Register shall be used in accordance with the WHS Risk Management Procedure. (9) When considering the design of risk controls (treatments) for refurbishment works, the hierarchy of control shall be applied as required by legislation. This is shown in Figure 1. (10) For refurbishment works, examples of possible treatments (mitigation) during design are shown in Table 1. (11) If the hazards cannot be eliminated, the most effective controls may be a combination of those shown in Figure 1. When completing the WHS Design Risk Register, the highest level of risk control (treatment) incorporated into the design shall be recorded in Column H. As design is an iterative process, the WHS Design Risk Register shall be updated if the design changes to record the improvements in safety made as the design progresses. (12) The WHS Design Risk Register should be completed in consultation with the relevant work area who will be using the working or learning space that is being designed. For larger projects, the external principal contractor may use their own risk assessment tools. Refer to the WHSMS Contractor Management Procedure for more information. (13) The WHS Design Risk Register should be checked and reviewed by a relevant Senior Manager within Properties and Facilities or another work area. (14) The University may make changes to this procedure from time to time to improve its effectiveness. If any staff member wishes to make any comments about this procedure, they should forward their suggestions to People and Capability. (15) Any staff member who requires assistance in understanding this procedure should first consult their Nominated Supervisor or Manager who is responsible for applying the WHSMS Implementation Procedure within their work area. Should further information or advice be required, staff should visit Service Central. (16) For related legislation, policies, procedures and guidelines and any supporting resources please refer to the Associated Information tab.WHSMS Safety in Design Procedure
Section 1 - Governing Policy
Section 2 - Application
Section 3 - Designer Obligations
Section 4 - ACU Designs
Section 5 - Designs Managed by Development and Capital Projects
Section 6 - Designs Managed by Property and Facilities or Work Areas
Hazard Identification During Design
Hierarchy of Control
Figure 1:
Table 1: Design Treatments (Mitigation)
Control
Design Mitigation
Elimination
Re-designing floor levels to remove an existing step, eliminating a trip hazard.
Substitution
Specifying water-based paints instead of solvent-based paints for the work – substituting the hazard with something safer.
Isolation
Specifying full enclosure around a hazard, such as fume cupboards.
Engineering
Specifying workshop equipment that is designed in accordance with AS/NZS 4024:2014, which will ensure appropriate guarding is incorporated.
Administrative
Ensuring Safe Work Method Statements or other procedures are specified where applicable.
PPE
Specifying Personal Protective Equipment (PPE) to protect workers from residual risks not controlled by the above controls for instance dust masks for tasks involving drilling.
Section 7 - Revision made to this Procedure
Section 8 - Further Assistance
Section 9 - Associated Information
View Document
This is the current version of this document. You can provide feedback on this document to the document author - refer to the Status and Details on the document's navigation bar.