(1) The primary aim of this Policy is to ensure that the University procurement practices, especially those relating to buying decisions (“Sourcing”), deliver value, leverage spend and meet the demands of probity. (2) This Policy establishes the five underlying principles in relation to the sourcing of Goods and Services, known collectively, for the purpose of this Policy, as the Procurement Pillars of Support. (3) These principles outline the deliverables required from the overall procurement process as follows: (4) This Policy applies to all ACU Staff in Faculties and Directorates across all ACU campuses. (5) This Policy imposes specific requirements on any staff members engaged in making sourcing decisions to buy University products. It specifies on which projects Finance and Planning are required to be consulted (according to project spend and importance) as regards the selection of supplier decisions. (6) Some important definitions: (7) The Spend on which Approvals and Sourcing decisions are based is the cost over the full term of the commitment. The decision steps in the process below describe who is authorised to make a Sourcing, or supplier selection, decision. (8) Final contract documents may only be signed by staff with the authority to sign on behalf of the University, in accordance with the Delegations of Authority Policy and Register, with the appropriate delegation limit to cover the spend over the term of the agreement. (9) Staff engaged in making the final Sourcing decision shall not be the final signatory in relation to making financial commitments. The person signing any financial commitment must be duly authorised by ACU to act on its behalf in accordance with its organisational responsibilities and the Delegations of Authority Policy and Register, with the delegation limit greater than or equal to the commitment being made over its full term. (10) Formal Requests for Tenders, Proposals and related documentation must be issued using the ACU tender portal eProcure (generally via Procurement), in the absence of other approved systems for this purpose. (11) If the value of a financial commitment over its term reaches the maximum purchase threshold, Finance and Planning must be informed of the Sourcing activity. If a formal tender process is not going to be used in the decision-making process, an exemption must be formally requested and approved. (12) Staff engaged in sourcing activities at ACU must comply with the requirements of Probity and divulge any potential conflicts of interest related to that activity – as set out in the document Procurement Probity Requirements with Conflict of Interest declaration to be completed and signed by the staff member. This includes where formalised activities are undertaken, which may involve a project team evaluation panel / tender committee. (13) Formalised Sourcing activities are required to follow the steps and utilise the enabling documentation as referenced in the Procurement Policy Sourcing Requirements. (14) Transactional Procure-To-Pay processes, including Purchase Order creation, can be found in the Purchasing and Procurement Procedure. (15) For sourcing activities with monetary commitments in Tier 3 (> $20,000 to <=$100,000) or above (per Section 4, Clause 23 of this Policy), where a tender process is not undertaken and a new supplier to ACU has been selected, the Minimum Requirements For Suppliers of Goods and Services to ACU - Shortened Supplier Version In Non-Tender Situations needs to be completed by the potential new supplier, with the completed form provided to Procurement for their records AND attached to the New Creditor Record form in TechOne at the point of onboarding. (16) Formal sourcing activities are required to follow the requirements set out in the Guidelines for Managing Logistics of Sourcing Project. (17) Where the Policy requires a formal tender process to be undertaken, then a decision as to whether this should be an Open Public Tender or a Closed Private Tender should be made in consultation with Procurement. (18) The Requirements for Vendor Management are as directed by Finance and Planning. Vendor management requirements for key supplier arrangements to ACU are as follows: (19) ACU is committed to tackling Modern Slavery practices at every level. The University’s sourcing processes, tender and other related documentation and templates include requirements for sustainable and ethical sourcing and anti-slavery requirements. Staff purchasers of University Goods and Services are required to take steps to identify and minimise any modern slavery risks and to take into consideration the principles of the commitments made by ACU towards Eradicating Modern Slavery and Human Trafficking and to ensure the suppliers: (20) ACU is committed to Reconciliation and Indigenous Advancement in line with Universities Australia Indigenous Strategy 2022-25, which makes a strong commitment to fairness and social justice for Aboriginal and Torres Strait Islander peoples. As part of this commitment, ACU aims to partner with Indigenous service providers to support the advancement of Indigenous peoples and their businesses across the supply chain. As such, ACU is a proud member of Supply Nation, the organisation that accredits Indigenous suppliers. As a result of this membership, a number of supplier relationships have commenced with approved Supply Nation suppliers. New suppliers are added to TechOne (and to ACU’s eMarketplace when the product is catalogue-suitable and as agreed with the supplier). Procurement will notify relevant staff of each new onboarded supplier’s offerings. Staff are encouraged to use the Supply Nation suppliers’ products or services, where suitable and appropriate. (21) ACU is a member of the University Procurement Hub (UPH), which offers the opportunity of source to contract cost savings by aggregating spend from participating universities across particular categories. Development of these category relationships is an ongoing process, with different categories being added. Please check with your relevant Finance Business Partner as to whether your sourcing project / product category is in a position to utilise this arrangement (which may negate the need to go through the quote / tender process). (22) Under this Policy, the following responses are required where a Preferred Supplier, Procurement Category Specialist, existing ACU Contract, existing appropriate Government Contract, or a suitable source to contact arrangement via the University Procurement Hub (UPH) is not available to cover the area of expenditure. (23) The Maximum Purchase Threshold is $100,000, as stated in the table below: (24) ACU, by virtue of its status, is allowed to buy against NSW Government rates and potentially other state government rates. To receive a discount from a NSW Government contracted supplier: (25) For other State Governments, follow the process below: (26) This Policy is an initiative of Finance and Planning and is supported by the Vice-Chancellor and President, Chief Operating Officer and members of the Executive. (27) The choice of what type of sourcing decision to make is based around the degree of financial commitment being made and in accordance with the Delegations of Authority Policy and Register. To this extent the following roles are afforded specific responsibilities, as follows: (28) These Roles and Responsibilities should be read in conjunction with the Procurement Roles and Responsibilities document. (29) Additional information to support the contents of this Policy may be found by reference to: (30) For questions, clarification, or any type of assistance in relation to this Policy and its ancillary processes, procedures, and related documents, please refer to the Finance and Planning Staff webpage.Procurement Policy
Section 1 - Purpose
Top of PageSection 2 - Application
Top of Page
Term
Definition
Procurement
the overall activity involving Sourcing and Purchasing.
Sourcing
the activities associated with what to buy and from whom to buy (e.g. the supplier selection process).
Purchasing
the transactional, administrative and systems-based activities associated with requisitions, purchase orders and their subsequent payment.
Product
a Good or a Service.
Section 3 - Principles
Section 4 - Commitment Levels and Required Actions
Top of Page
Requests for Exemptions
Section 5 - Use of Government Contract Rates
Top of PageSection 6 - Roles and Responsibilities
Section 7 - Further Assistance.
View Document
This is not a current document. To view the current version, click the link in the document's navigation bar.
Value Of Commitment Over Term
Required Response
<= AUD$5,000
Stakeholder makes own decision in accordance within their delegation limit as outlined in the Delegations of Authority Policy and Register.
> AUD$5,000 to <= AUD$20,000
Stakeholder receives two written quotes and makes final decision within their delegation limit as outlined in the Delegations of Authority Policy and Register.
> AUD$20,000 to <= AUD$100,000
For any spend over AUD$20,000, the stakeholder is required to inform their Finance Business Partner, to ensure they:
For spend > AUD$20,000 to <= AUD$50,000, written quotes (outside of the tender process) must be received from at least three potential suppliers.
For spend of > AUD$50,000 to <= AUD$100,000, generally either an RFQ, RFP or RFT is required to be sent using the ACU Tender Portal eProcure, to a minimum of:
Tenders are generally released as Public tenders, however Private tenders (to a select group of invitees only) may be considered in certain circumstances, such as to limit the reach of ACU confidential information necessary to quote.
Finance and Planning (Procurement) holds all template tender documents, and can provide the correct tender documentation for use, depending on the type and scope of the product / service.
ACU tender documents are listed below in order of complexity:
RFQ – The Request for Quotation document is generally less complex, targeted primarily on pricing and is used when inviting potential suppliers to submit competitive pricing for specific products.
RFP – The Request for Proposal document is a formal method of receiving detailed and comparable proposals from potential suppliers. It provides required information needed to make an informed purchasing decision. It is often used when seeking solution-based offers. It is slightly less formal and somewhat more flexible than an RFT.
RFT – The Request for Tender document is a formal invitation to potential suppliers to submit an offer to supply goods or services against a detailed tender. It is focused on both price and quality, and is generally used for more complex and detailed projects than an RFQ or an RFP.
> AUD$100,000
(Maximum Purchase Threshold)
Stakeholder informs their Finance Business Partner, who will inform / liaise with Procurement to ensure a correct process is followed.
A TEC is required to be formed unless approval to not use a TEC is obtained from:
RFTs and RFPs are required to be sent using the ACU Tender portal eProcure. Procurement will provide the correct tender documentation for use, which will have been pre-approved for use by Procurement - who will have consulted with Office of General Counsel (OGC).
RFPs and RFTs are required to be sent to a sufficient number of potential suppliers that will result in at least three (3) responses – as below.
Requests for exemption from sourcing spend requirements, are required to be sought for any category of spend ($AUD$5,000 to <= AUD$20,000, > AUD$20,000 to <= AUD$50,000, > AUD$50,000 to <= AUD$100,000, > AUD$100,000) in the rare cases where the staff requestor believes and can justify that not adhering to the specific spend limit’s rules will represent a better outcome for ACU. NB: Exemption requests are scrutinised carefully by Finance / Procurement, who may seek further supporting information and / or comparison figures. There is no guarantee the exemption will be approved.
All exemption requests must be accompanied by a completed and signed ACU Procurement Probity Requirements, with Conflict of Interest Declaration from each staff member involved in the project’s supplier evaluation and decision process.
Requests for exemptions, whereby the proposed supplier is new to ACU, must be accompanied by the two following documents which have been completed by the nominated supplier:
The submitted documents form part of the exemptions package reviewed by Procurement and presented to the CFO and / or COO (based on spend limit requirements) who have final authority to approve the exemption, as per the spend limits.